Renovation log for December 1-7


Monday December 2:
Siding work around the front door/picture window.


Tuesday December 3:
Drywall taping and first coat of compound done. Baseboard radiators installed on the second floor and connected to the boiler. Porch lattice installed.
Taped in 1 bedroom. And another. Baseboard radiators going in. Porch bottom is now covered.


Wednesday December 4:
More drywall and siding work. Second floor heating zone wired up and running. Interior walls on the first floor next to the stairs are removed.
It so open now. Michael wants to help.


Thursday December 5:
More drywall and siding work.
South wall is done. Neither wind or snow or rain.... ...will keep these guys from siding.


Friday December 6:
More siding. Stairway drywall is hung.
Finishing up the West Wall. Walls on second floor stairs. And the cellar stairs.


Saturday December 7:
Drywall sanding begins. More mud or stairway drywall.