Sunday December 15:
Bathroom Ceiling gets second coat of paint.
A white bathroom.
Monday December 16:
Hallway is primed.
Looking up the stairs.
Tuesday December 17:
Siding work. Our bedroom is primed. Start of new electrical service work.
Our bedroom.
Wednesday December 18:
Siding work. Andrew's bedroom and Daniel's bedroom are primed. New 200 Amp Electrical service is hooked up.
Andrew's room.
Daniel's room.
New breaker panel.
Inside the front porch is done.
Thursday December 19:
Siding work. The playroom is primed.
The playroom.
Outside of the side porch is done.
Friday December 20:
Michael's bedroom is primed. All priming is complete.
The last wall in Michael's room.