Renovation log for January 12-18


Sunday January 12:
Trim sanding, staining and urethaning.


Monday January 13:
Bathroom window is trimmed and doors are installed. Bathroom floor gets prepared for tiling. Electrical and phone outlets are installed. Trim staining and urethaning.
Starting the finish work.


Tuesday January 14:
Bathroom ceiling light/exhaust fan installed. Ceiling fans installed in 3 rooms (lights are still on order). Phone and cable outlets installed. Trim sealing. Door and door jamb sanding.
Lights in the hall. Lights in the living room. One of the fans.


Wednesday January 15:
Bathroom floor tile is laid. Trim urethaning.
Looking more like a floor. Trim ready for urethane.


Thursday January 16:
Bathroom wall tile is started. Sink and medicine cabinet are put up. Window trimming. Trim sanding. Trim and door jamb staining.
Start of the walls. Sink and medicine cabinet. Windows are looking more finished.


Saturday January 18:
Door and door jamb sanding. Door sealing. Trim and door jamb staining.