Sunday March 23:
Blinds put up in the upstairs bathroom (replacing a temporary shade). Most of the rest of the downstairs floors get cleaned and waxed (except where furniture is in the way). More clean up and staining the old molding so it can be reinstalled on the first floor.


Monday March 24:
The rest of the downstairs floors get cleaned and waxed.
The floors are clean again.


Tuesday March 25:
Plastic gets put down on the first floor to ready for painting the ceiling.


Wednesday March 26:
The first floor ceiling gets 2 primer coats.
The ceilings are white again. This one too.


Thursday March 27:
The first floor ceiling gets its final coat. The old kitchen floor is ripped up and new plywood is put in.
The ceilings are done. This almost looks better than the old floor.


Friday March 28:
The new kitchen floor is installed.
Putting the floor down. Now it really looks good.


Saturday March 29:
More cleanup on the old molding.