Tuesday November 12:
The last of the windows are put in, both upstairs and downstairs. Old siding is removed from the south side of the
house. Temporary stairs are built to the porch. Rough plumbing and electrical are completed.
Drain is connected.
Wednesday November 13:
Most of the rest of the old siding is removed. Outside of the upstairs windows were framed
to match the downstairs.
A tar paper shack.
Thursday November 14:
The conduit for the electrical service to the garage is put in. More termite damage is found under the tar paper.
Some inside Views.
View from South East.
View from North East.
View from North West.
View from South West.
More munching termites.
Friday November 15:
Lot's of yard cleanup. The siding person came and set up his work area.