Monday November 18:
Foam insulation is started on the outside wall.
Some insulation.
Tuesday November 19:
Siding is started. Insulation is put in on the second floor. The lattice pieces for the new
porch was built. The old side porch was roofed.
A Beginning.
Walking tall.
Last of the roof.
Wednesday November 20:
More siding. More termite damage repaired. Old interior stairs are demolished. New
temporary stairs to the second floor are built and new stairs to the basement are built.
The attic pulldown stairway is installed.
Stairs leaving.
New stairs being built.
New basement stairs.
Temporary second floor stairs.
More siding.
Thursday November 21:
More siding. New basement door put in. Drywall arrives.
More siding.
Friday November 22:
Heidi works on painting the porch lattice.