Monday November 4:
Heidi works on the trim pieces.
Tuesday November 5:
Most of the second floor windows are put in. Electrical wiring and boxes galore! Rough
plumbing and heating pipe work for the second floor started. The last of the walls were framed.
That big triple window.
Wiring is started.
Wednesday November 6:
More rough plumbing. All pipes leading to the second floor are now in. Old front cement stairs
and stoop are demolished. Old termite damage is found in the wood behind the stairs. The
new front porch roof is framed in. Posts are installed in the basement and the floor is patched.
Installation of first floor replacement windows is started.
Stairs going
going
going
going
Gone!
Termite Damage.
Porch Roof.
Thursday November 7:
More rough plumbing and electrical. Rough heating pipes are in on the second floor. Rough plumbing
for the bathroom is finished. The vent stack is poked through the roof. Water feed pipes are hooked
up in the basement. Lots of electrical wiring is done. The termite damage is repaired and the porch
floor is framed. Most of the first floor replacement windows are completed.
New Kitchen Window
Building the porch Deck.
Daniel is using it already!
Friday November 8:
More rough electrical. Lots more electrical/cable/phone wiring is done. Most of the upstairs rough
electrical is completed. Main roof shingles are completed and the porch roof is
shingled.
Roof is complete.