Renovation log for October 13-19


Monday October 14:
The dumpster arrives.


Tuesday October 15:
Framing lumber arrives. The chimney is extended so that it will reach the level of the new roof. Insulation is pulled out of the attic. The house service wires are put onto a temporary pole.


Wednesday October 16:
New Beams are installed in the basement. The basement floor is cut for the cement footings that will receive the new posts. Cement dust everywhere!

Hole 1 Hole 2 Holes 3 and 4

Thursday October 17:
The current attic/roof is taken off. Some of the new floor joists for the second floor are put in. The Windows arrive.

Roof is gone. Attic Door opens to outside!. View in front. View in back.


Friday October 18:
Joists and the subfloor for the second floor are put in. More lumber shows up.

Subfloor Subfloor


Saturday October 19:
More work on the second floor subfloor.