Renovation log for December 8-14


Monday December 9:
Siding work and some drywall mud/sanding.


Tuesday December 10:
Siding work and final second floor drywall sanding.


Wednesday December 11:
Siding work. Stairway to cellar has side rails put on. General cleanup.


Thursday December 12:
Siding work. Bathroom is primed.
Getting closer. Even the old porch.


Friday December 13:
Siding work. Cutting Interior Window Trim. Bathroom ceiling and closet get first coat of paint. Start priming hallway. Front porch stair railings are finished.
Getting the trim ready. Closer Still.