Sunday January 19:
Door urethaning. Door jamb staining. Trim and door jamb sealing.
Monday January 20:
Tile work. Complete window trimming. Lights are installed on ceiling fans, and fan and light put up in one more room. Trim and door jamb sanding.
The big triple window.
A typical single window.
Just a few more pieces and accesories...
...are needed to finish.
One of the fans with the light.
Tuesday January 21:
Trim and Door urethaning. Door jamb staining. Door and door jamb sealing.
Wednesday January 22:
Toilet, faucets for the sink and tub, and the shower head are installed. Door and door jamb sanding. Door jamb staining. Door jamb sealing.
A Compact Toilet.
Tub faucet.
Shower head.
Roma Marble vanity top and faucet.
Thursday January 23:
The rest of the bathroom tile and accessories are put up. Door and door jamb sanding. Door and door jamb urethaning.
Bath/shower towel holders.
Bath long wall with soap dish.
Sink towel holder.
Heidi making a door look good.
Friday January 24:
Gutters are installed. Door jamb sanding.
Saturday January 25:
Door jamb sanding and staining.